Which work centre is holding the plan up, how much time it would take to fix, and which orders that would move.
The Capacity page answers three questions in order: which work centre your late orders are queueing for, how much more time it would take to clear them, and which orders that time would actually move. The second and third answers come from running the scheduler again, not from a formula.
Load, used and free follow the period selector. Queued, waiting and late orders cover the whole plan: an order that misses its date in four months is still waiting for the same work centre.
Pick a work centre. You set how the extra time is added — weekend shifts or longer days — and for how many weeks, because a plant runs Saturdays until October, not forever. The dates the arrangement covers are shown, and the hours exist only inside them.
Work out how much then runs the plan at rising amounts of added time and stops when two steps in a row buy nothing. Each row reports how many orders are still late, the on-time percentage, and what the whole arrangement costs in hours. You can also type a number in yourself and run just that.
The answer comes back in one of two forms, and the second is the more useful one:
The second saves you buying a shift that changes nothing. It happens because clearing one queue moves the constraint to whatever is next — which is also why a row that barely moves is a real answer rather than a failure.
Alongside more hours you can let some of the work go elsewhere: a second machine of the same kind, or a work centre APS proposes because your own routings already run the same operations on both. The proposal is read off your history, not guessed — but the same operation name is not proof of interchangeability, and only the shop knows whether “Cut” on one machine is the same cut as on another.
Pick a row in the results to see the orders behind the number: order and sale order, the date it finishes before and after, and how many days it moved. Orders that stop being late are marked, and so are the ones the reshuffle sets back — hiding those would make every trial look like a free win.
Days are counted between the dates shown, not between timestamps, because a job that moves from Tuesday afternoon to Sunday night has moved two days in the only sense a planner reads.